Key Milestones
-
1986
Kilang Getah Hock Guan (“KGHG”) a partnership was established by Er Hock Lai and his brothers Involved in the processing of crepe rubber -
1989
Acquired SFT involved in the trading of various grades of crepe rubber and house grade block rubber Expanded business overseas Gradually ceased processing crepe rubber -
1994
SFT acquired Kilang Getah Hock Guan consolidating business operations of both entities -
1996
SFT acquired STG, which owned the Gemas land Began construction of Factory 1 with production floor space of ~128,000 sq ft -
1997
Completed construction of Factory 1 Started to produce SMR Grade -
2000
Purchased new machinery -
2003
Received first ISO certification which was the ISO 9001:2000 certification from Lloyd’s Register Quality Assurance Inc -
2005
Expanded warehouse in Factory 1 and set up laboratory to conduct quality control and research and development activities in-house Completed construction of Factory 2 comprising of a production floor space of ~101,000 sq ft -
2007
Laboratory was approved by MRB as an authorised SMR laboratory which enables us to conduct in-house quality control inspection and issue quality control inspection certifications for block rubber Installed new machinery for Factory 2 which added 25,000 MTS to our production capacity -
2008
Completed construction of Factory 3 with production floor space of 90,000 sq ft -
2012
Installed new machinery line for block rubber production in Factory 3 -
2022
Installation of Solar System for renewable energy to suppty electricity to our factories. Successful listing on the Main Market of Bursa Malaysia a on 7 July 2022. Optimised our production by increasing our total annual capacity to approximatety 150,000 MTS per year through adding a second working shift in Factory 3. -
2023
Optimised our production by increasing our total annual capacity to approximatety 166,000 MTS per year through adding a second working shift in Factory 2. -
2024
Optimised our production by increasing our total annual capacity to approximatety 190,000 MTS per year through adding a second working shift in Factory 1 Installation of Biomass System for renewable energy by replacing the consumption of diesel as a fuel for our dryer system in the factories Successful completion of both Private Placement and Bonus Issue exercises on 26 April 2024 and 10 June 2024, respectivety -
2025
Comptetion of the installation of the Smart Rubber Manufacturing Equipment in Factory 2